FLAP Project - Mitchell St. & Black Rock Rd.

 

Project Overview

Project Description:

This project consists of grading, drainage, base, paving, walls, and construction of a 1-span, 113-foot long precast, prestressed concrete deck bulb-tee girder bridge. Abutments are founded on spread footings. The work also includes construction of a temporary detour bridge and demolition of the existing steel truss bridge.      

Click HERE for a Monthly Project Update

Click HERE for Travel Restrictions

Click HERE for Scheduled Outages

Project Cost: The estimated project cost is $7,000,000-$10,000,000.
Project Schedule: 

Tentative Completion Date:  Fall/Winter 2024 

Click HERE for a Project Schedule Summary

Click HERE for a 3-Week Schedule Forecast