2023 Chip Seal Project

During the month of July, Polk County Public Works will be completing Chip Seal projects in the South County and West Salem areas. Crews will be applying a chip seal and fog seal to the County roads listed below. More information on the chip seal process can be found here. There will be delays intermittently during this time period.  Work hours will generally be between 7:00 A.M. and 6:00 P.M. All work is dependent on weather.

At this time we plan to complete pre-sweeping July 6. There are candlestick cones lining the streets in residential areas to indicate no parking. Once those are moved to the backside of the sidewalk, it means the sweeper has already come thru the area and you can resume parking on the street until the chip seal project starts. 

The Chip Seal project will be completed July 10 - July 29, 2023. A more detailed schedule will be updated on the Polk County Website  at www.co.polk.or.us/pw when a more accurate timeline is determined.

What You Can Expect during CHIP SEAL:

Drivers - During treatment, roads will be reduced to one lane of traffic.  Drivers should expect some delays, but roads can be driven on a few minutes after chip sealing.  All lanes will be open to reduced-speed traffic at the end of each work day. PLEASE DO NOT DRIVE ON FRESH OIL. To avoid getting oil on your car, drive and stop slowly, and avoid turning your wheel while in a stopped position.  

Pedestrians/Bicycles - Pedestrian and bicycle traffic will not be permitted in the area temporarily for the duration of the project due to safety concerns.  

Residents - Street parking will not be allowed for the duration of the project. As the operation passes your property, there will be a window of time in which you cannot exit your driveway. This will not last more than 20 minutes. We will provide advanced notice of when project will occur to minimize impact to residents.

We realize these pavement preservation projects may create some inconvenience for residents, pedestrians, motorists and businesses.  The County thanks you for your patience and cooperation as we work to preserve our roadways.

If you have any additional questions, Polk County Public Works can be reached at (503) 623-9287.

Chip Seal Project Roads (South County) 

BUENA VISTA ROAD
CLOW CORNER ROAD
CORVALLIS ROAD
DAVIDSON ROAD
MAIN STREET (BUENA VISTA)
OLD FORT ROAD
PARK STREET
PARKER ROAD
PRATHER ROAD
RIVERVIEW STREET
SEQUOIA STREET
STAPLETON ROAD
SUVER ROAD
TALMADGE ROAD
WELLS LANDING ROAD
WIGRICH ROAD
WILLAMETTE FERRY STREET

Chip Seal Project Roads (West Salem) 

29th Place NW
30th Court NW
30th Place NW
31st Court NW (North)
31st Court NW (South)
32nd Avenue NW
Caribou Court NW
Cheyenne Court NW
Commanche Court NW
Fernwood Court NW
Glen Creek Road NW
Jay Court NW
Lakeview Court NW
Lakeview Drive NW
Lakeview Place NW
Willow Creek Drive NW